10/05/2010
By Charlie Henderson
Every project presents different challenges, but sometimes one stands out because of its scale, complexity or schedule. One of these was building the world's largest polysilicon plant for Jiangxi LDK PV Silicon Technology Co. Ltd. (www.LDKSolar.com) in Xinyu City in the People's Republic of China—and doing it in record time. In fact, just 24 months after breaking ground in August 2007, one of the $1.2 billion plant's three production lines produced its first product on Sept. 8, 2009.
Because it is the largest facility of its type anywhere, LDK Solar's polysilicon plant is divided into three major areas: polysilicon production, off-gas recovery and trichlorosilane production (Figure 1). The plant is designed to have an output of 15,000 metric tons per year from its three production lines. In each production line, there are reactors and converters. Production starts with sand, which is processed using hydrochloric acid, and then further purified to produce solar-grade polysilicon. This material is in high demand by photovoltaic cell manufacturers, which is why the plant had to be built so quickly.
ADVERTISEMENT
With such a huge project and such a short time frame, it was clear that normal project schedules (which are based on designing the process, designing and engineering the plant, raising specification sheets for all the instruments and placing orders with suppliers) would not be possible. There simply wasn't time. This fast-track project required our team at Fluor (www.fluor.com) to do things differently. Still, as with any project, we took the three-legged stool approach, which balances quality, cost and speed. We knew that we couldn't compromise on safety or quality, but we were prepared to let speed override cost considerations.
Given the rapid pace of the project design and the repeat setup among the production lines in the process, we had to be flexible in our approach to project planning. During the design, one set of process and instrument drawings (P&IDs) were developed for the first reactor and converter in the polysilicon production area. A P&ID numbering scheme was then developed to allow for sequential numbering of the subsequent reactor and converter P&IDs for the remainder of the polysilicon production lines. For convenience and reference, instrument tag numbers incorporated a portion of the P&ID numbering.
Highly structured, custom spreadsheets rather than the more typical specification sheets were designed and used to organize and order the instrumentation. Spreadsheets helped quickly organize instrumentation requirements, with columns serving as the design parameters necessary to aid in selecting the appropriate model, including process fluid, fluid state, pipe specification, design temperature and pressure, projected flow rates. Spreadsheets also were a good reference for the instrumentation quantities required for each line. The tag numbering sequence was shared with the vendors, so the implied tags for additional quantities were known.
In addition, from prior experience, we knew there would be many instruments requiring SIL 2 ratings. This was also included in the tracking spreadsheet. Changes that cropped up were addressed by a simple revision to the spreadsheet, rather than requiring revision to multiple datasheets.
Finally, the speed of the project required us to begin ordering instrumentation prior to the availability of process data and the results of hazardous operation reviews. Our tracking spreadsheet provided a clear overview, both of what was required and when it was needed for the plant construction phase of the project.
It was identified early that the success of this project depended on quality of construction and control system and instrumentation vendor selection. Especially with such a short timeline, supplier selection must be managed carefully. We needed partners with strong technical and engineering support capabilities, and the ability to meet delivery commitments.
As a result, Emerson Process Management's (www.EmersonProcess.com) broad product line, dedicated personnel and experience doing business in China were key factors in its selection by Fluor as the main automation contractor. Within its PlantWeb digital plant architecture, the DeltaV digital automation system would serve as the polysilicon plant's distributed control system (DCS) for process control, its DeltaV SIS process safety system would be used for safety-related I/O, and its AMS Suite maintenance software would be used for managing calibration and diagnostics. Emerson personnel would also be involved in system integration and commissioning. Also, the PlantWeb architecture included Micro Motion Coriolis mass flow and density meters, Rosemount temperature and pressure transmitters, and Fisher control valves (Figure 2).
The fast-track pace of the project, coupled with the requirement for almost 2000 flow data points, necessitated that we use flow technologies with which we had experience and which we knew could meet the many plant requirements. The aggressive planning timelines meant we had to deal quickly with undefined process data, while balancing this against known plant and operational constraints.