Portraits of Simulation Success

Three End Users Employ Several Types of Simulators from Invensys to Improve Design, Training and Operations in Power, Mining and Other Applications

Share Print Related RSS
Page 1 of 2 « Prev 1 | 2 View on one page

By Jim Montague

Now, don't get distracted. There's a lot more to simulation than pretty pictures. Likewise, simulation has a much longer and more varied history than those colorful CAD/CAM images, and its future is likely be even more diverse than its past.

Of course, process simulation first grew out of the natural and longstanding desire to speculate and project what was most likely to happen next in many applications in an effort to improve them and avoid potential problems and accidents. Now, as more sophisticated and faster information and data processing became available, simulations have evolved from static recommendations to increasingly dynamic operational aids.

Taking Care of Turbines

For instance, Tucson Electric Power Co.'s (TEP, www.tucsonelectric.com) Springerville Station recently needed new controls for its two 380-megawatt, coal-fired, net-combustion engineering drum boilers with an ABB steam turbine. The station also needed an upgrade to include overfire air, low-NOx burners and new hydraulic actuators for the turbine stop/control valves. TEP is the principal subsidiary of UniSource Energy and serves more than 375,000 customers in southern Arizona.

To help avoid possible errors that might delay start-up and service or potentially cause damage, TEP's engineers included detailed control checkout functions on a high-fidelity simulator for the station's new control system, and then also used it for operator training. As a result, they selected Invensys Operations Management's (www.invensys.com) Foxboro I/A Series distributed control system (DCS), which was a major shift from its former, bench-mounted analog controls.

Invensys reports that it has pioneered a virtual simulation approach by modeling control systems using its FSIM Plus simulation of the I/A Series DCS. This method uses actual I/A Series controller algorithms and HMI and DCS configuration tools to provide the most accurate representation of the control system. For example, TEP's staff now has the capability to move the controls and graphics back and forth between the simulator and control room, making the simulator a complete I&C device.

In addition, for TEP's new Alstom turbine control valve actuators to be guaranteed, an Alstom turbine control system also had to be part of the configuration. This led to questions about interfacing to the I/A Series DCS, I/O, turbine protection and operator controls. So, using FSIM Plus, the project was modified to include a connection to GEIP's PLC 90-70 and 90-30 controllers, which ran the Alstom turbine control system programs.

Also, TEP's new simulator and DCS designs went through concurrent development with major DCS loops tested and pre-tuned in the simulator. Feedback from operators using the simulator was then used to fine-tune graphics and make control function changes based on TEP's operating procedures.

The simulator was on-site at the Springerville Station for six months of factory acceptance testing before the new DCS was installed in Unit 1, and it identified and allowed fixes of more than 350 errors before they reached the new controls and the plant.

"Most of these problems were minor, such as graphics configuration errors and simple point misconnections. However, without the simulator, these errors would have been found during critical testing on the live unit," says Chris Wallace, TEP's simulator project manager. "Even simple configuration errors take significant unplanned downtime to find and fix, especially in that high-pressure environment."

Another value of the simulator came when merging the I/A Series DCS and Alstom's control systems. Even though the running turbine and simulator were not connected, initiating the Alstom turbine using the simulator also prevented dozens of interfacing problems. "It saved at least one week of start-up time due to the operator's familiarity with the controls and advanced understanding of how they should interact with the unit," adds Rex Brown, TEP's project manager for the DCS retrofit project.

Mimicking Mining

Logically, one of the emerging truths about simulation is that if the data is specific, accurate and appropriate, then the resulting images of it have the best chance of being genuinely useful.

For instance, to help its mining clients in and around Brisbane, Australia, engineering consultant Meteng Pty. Ltd. (www.meteng.com.au) develops process models and simulations, and recently used Invensys' Wonderware software to create a virtual, interactive environment where its users can design applications, practice scenarios and learn by doing. Meteng calls its solution the Walk-Through Interactive Simulated Environment (WISE). It uses Wonderware's software to process dynamic mathematical data models, display on high-resolution screens in a 3D "cave," and simulate an actual processing plant, including a prototype SCADA and control system (Figure 1).

Though WISE also integrates Apple and Microsoft technologies on its displays, Wonderware's software serves as the main control center and opens the 3D models, loads dynamic processes and initiates or saves training scenarios. Specifically, Wonderware's InTouch Human Machine Interface (HMI) adds a GUI for the WISE SCADA system, while Wonderware's InControl software provides expandable control and scripting that supports the system's interlocks and logic control.

Page 1 of 2 « Prev 1 | 2 View on one page
Share Print Reprints Permissions

What are your comments?

You cannot post comments until you have logged in. Login Here.

Comments

No one has commented on this page yet.

RSS feed for comments on this page | RSS feed for all comments