Kevin Kelley learned the value of control system lifecycle management the hard way.
Following three losses of control system power in 2012, the process control foreman at Solvay Chemicalâs Green River soda ash production facility in southwestern Wyoming oversaw the long-delayed replacement of the unitâs heretofore âuninterruptibleâ power supply (UPS). Replacing the UPS itself went smoothly, but then 64 of 300 associated control system power supplies failed to power back up. After not a little scrambling to keep the unit up and running, the team discovered that the 14-year-old power supplies in question had a recommended replacement interval of eight years. âIt really bit us,â Kelley said.
So began an ongoing journey at Solvay Green River to better understand and proactively manage the lifecycle status of the plantâs process control systems. Kelley shared Solvayâs story in his best-of-conference presentation, âSolving the Lifecycle Management Equation,â at this weekâs Yokogawa Users Group conference in Orlando. Today, the plantâs CENTUM VP R5 system from Yokogawa encompasses some 12,000 I/O points, 22 Field Control Stations, 17 operator stations, six engineering stations and eight plant servers. Further, it controls processes spread out across 20 miles.
Staying current a challenge
[sidebar id =1]âIndustrial control systems are put into operation with the expectation of long-term performance, often spanning many years,â Kelley said. During that long lifecycle, maintenance requirements often change due to factors such as innovations in technology, new releases in software and hardware, end of support for certain components, and technology refresh cycles for workstations and servers. And for modern control systems that use Microsoft Windows operating systems, patches and security updates represent an added burden. Other complicating factors include system and software release and revision cycles, backwards compatibility with older systems, as well as availability and support of hardware components.Â
Because of these many challenges, end-users need a simple way to understand the ever-changing environment of control system lifecycle management, Kelley said. âAs a manager itâs my job to get the most value possible out of our control system investments. Users such as Solvay must be able to define a lifecycle strategy for their control systems that provides them the best return on their investment without sacrificing system security or reliability.â
Lifecycle report boosts visibility
Even as Kelley and Solvay struggled to get a better handle on the lifecycle status of the plantâs automation assets, Yokogawa had begun preparing a lifecycle management report that would facilitate far greater visibility into the roadmap and future support requirements of those assets.
Each of Yokogawaâs new Lifecycle Reports is specifically prepared for each userâs system, explained John Gracia, manager of Yokogwaâs Techncial Assistance Center near Atlanta. âWith this report, the customer can see where they are in the lifecycle of each system component, including maintenance and support options available as elements move from current release to maintenance and on to âbest effortâ support and obsolete phases. With this information, they can better plan and understand Yokogawaâs support policies for the related system products.â Kelley particularly appreciates a color-coded Gant-style summary chart that shows where each system component currently stands in its support lifecycle. Red, yellow and green coding clearly indicates how close each element is to requiring attention.
âWeâre looking to develop a 20-year vision for the future of the plantâs control system assets,â Kelley concluded. âWe are in the middle of the process now and Yokogawa has provided us with a tool that takes much of the work out of defining this path. We believe a well-defined path will save us valuable time in maintaining our control system and it will give us the peace of mind that we have made a great effort to help keep things from slipping past us in the future.â